SechoirMec
Freedom bar

Wood dry kiln that we have achieved

Projects executed by Mec Dry Kiln Inc.
Mec Dry Kiln wishes to thank all its loyal customers for their confidence.

Lic. RBQ. : 8277-6576-12

 

Projects completed by Mec Dry Kiln during year 2011



Séchoir et rabotage du Lac Vert inc., Hébertville, Québec
Automatisation of 4 existings kilns and 1 existing High steam pressure Boiler.



Abitibi Bowater, St-Félicien, Québec
Repairing a Secovac existing kiln.



Fontaine Lumber, Woburn, Québec
Repairing an Salton existing kiln.


Tembec, La Sarre, Québec
Repairing a an existing kiln.

 

Scierie Leduc, St-Emile, Québec.
The renovation of an existing kiln.

Menuiserie Des Pins Ltée., Notre-Dame-Des-Pins, Québec
The construction of 2 new hard wood dry kilns, capacity of 60 000 Pmp. each.  Automatisation of 4 existings Dry Kilns.



Back to top

 


Projects completed by Mec Dry Kiln during year 2010


Freedom bar
Fornebu Lumber Sawmill
, Brunswick Mines, Nouveau-Brunswick. The construction of 2 new softwood 2 zones dryers with a capacity of 150 000 FBM each.

Freedom bar
Serex , Amqui, Quebec. The construction of one dry kiln, 3 000 Pmp capacity.

Freedom bar
Barrette Wood , Saint-Jean-sur-Richelieu, Quebec. The construction of 2 new softwood 2 zones dryers with a capacity of 150 000 FBM each.

Rénovation P. Baillargeon
Saint-Raphael, Quebec. The construction of one hard wood dry kiln, 3 000 Pmp capacity.


Freedom bar
Alsero Ltée , St-Janvier, Mirabel, (Quebec).
The construction of one kiln,with 800 pallets capacity.
Freedom bar
Défense nationale , Montreal, Quebec. The construction of one kiln for HT Treatment.

Freedom bar
Fraser Paper , Plaster Rock, New Brunswick. Fraser Paper, Plaster Rock, New Brunswick. The construction of 2 new softwood single pass 2 zones dryers with a capacity of 324 000 FBM each and 2 heat exchangers installed per kiln.

Back to top

 

Projects completed by Mec Dry Kiln during year 2009


Freedom bar
Pelletier Equipement Ltée , Lac Baker, New Brunswick.
The construction of a small fired wood kiln with high-pressure steam energy.

Freedom bar
Portbec, division Produits Forestiers D.G. , St-Aurélie, Québec.
Enhancement of two dry kilns.

Freedom bar
Groupes Gds , Matane, Quebec.
Following a fire, Mec dry Kiln was hired as a contractor for the construction of a new high pressure steam boiler and the conversion of existing kilns.

Back to top

 

Projects completed by Mec Dry Kiln during year 2008


Freedom bar
Les Planchers Mercier Inc., Drummondville, Quebec
The construction of 6 new hard wood dry kilns, capacity of 85 000 Pmp.  each

Scierie Fortin Inc. St-Isidore, Quebec
The construction of 1 small capacity kiln.

Freedom bar
Chassé Inc, Ste-Marie de Beauce, Quebec
The construction of a kiln pallets on rails with a capacity of 500 pallets.

Freedom bar
Sartigan Inc, St-Honoré, Quebec
Dismantling, removal and construction of 2 dry kilns with a capacity of 185 000Pmp each.

Freedom bar
Boisaco Inc, Sacré-coeur, Quebec
Dismantling, removal and construction of 2 dry kilns with a capacity of 225 000Pmp each.

Crabbe H.J. & Sons, Bristol, New Brunswick
automations of 2 existing dry kilns.

Back to top